Its not.
While its great to see people (finally) on the ride, they still have not cycled the ride with multiple trains at the same time. They are struggling to get the rides rotation programing to be consistent on the two trains they have on the track, and there are more trains that have to be programed and commissioned. There is no way they open this ride with only 2 trains available to operate.
I would expect to see soft openings in late June with opening in July or August, assuming they don't run into more issues with the ride.